NCDOT Beaufort Co C204219: Bridge # over Norfolk Southern Railroad on US-17 BUS, and Bridge # 25 on US-17 BUS Over Pamlico River C204219

by June 11, 2019

ADVERTISEMENT FOR BIDS

REQUEST FOR QUOTE FOR CONSTRUCTION
OF NCDOT BEAUFORT CO C204219:
BRIDGE #3 OVER NORFOLK SOUTHERN RAILROAD ON US-17 BUS,
AND BRIDGE #25 ON US-17 BUS OVER PAMLICO RIVER C204219
RESPOND WITH YOUR INTENT TO QUOTE

Contacts / Respond to:
Thalle Construction Company. By Jun 16,2019 10:00 am C/O: Adrienne Duncan quotes@thalle.com or aduncan@thalle.com  (P)919.241.1635).

Project Description:
GRADING, DRAINAGE, PAVING, AND STRUCTURES, 0.622 MILES and includes major actives and specialty items; Borrow Excavation, Reinforced Concrete Deck Slab, Class A Concrete Bridge, 54″ Prestressed Concrete Girders, Guardrail, Signing, Pavement Markings, Erosion Control, Reforestation, Signals/ITS systems.

Bid Documents:
Are available from Thalle Construction online plan room https://secure.smartinsight.co/#/PublicBidProject/1906066 can also be obtained/viewed by appointment at NCDOT Division offices, NCDOT central letting webpage, Construction Resource Center(s) of NC, and at Thalle’s office in Hillsborough NC.

Divisions of work:
Office-trailer, sanitary services, surveying, earthwork, concrete, rebar, SIP deck, piping, clearing and grubbing, Pilings, asphalt, stone and aggregates, erosion control, traffic control, signage, trucking, electrical, permanent signage, reforestation, seeding, bridge repair/ concrete repair, utilities installation, geotechnical services, pavement striping, guard rails, fencing. Asbestos Assessment, shotcrete, prestressed concrete girders.

Project Start:
OCT 15TH 2019

Completion:
JAN 28TH 2022

NOTE PROJECT DOCUMENTS INTERMEDIATE CONTRACT TIME & RESTRICTIONS:
#1 Planting & Vegetation Start OCT 15TH & COMPLETE August 1st 2021
#2 MOT Day & Time Restrictions: US 264 (Pactolus Hwy) and US 17 South Off Ramp
#3 MOT & Overhead Signs Day & Time Restrictions: US 264 (Pactolus Hwy) and US 17 South Off Ramp
#4 TMP Steps and maintain Traffic 180 Days

Business Utilization:
MBE/WBE/DBE firms are encouraged to participate & will be listed at time of bid, Work & materials may be combined or divided to facilitate maximum participation. Subcontractors are obliged to sublet to 2nd & 3rd tier DBE subcontractors. DBE firms needing assistance with obtaining bonding, loan capital, lines of credit, insurance, quickpay & payment-agreements, obtaining equipment & supplies materials or negotiate joint venture & partnership arrangements can contact Thalle for assistance. Thalle will negotiate fairly with interested DBE firms & will not reject firms as unqualified without sound reasons-based capabilities.

 