High Point Center for Active Adults project in High Point, NC
PREQUALIFICATION ADVERTISEMENT
Blum Construction has been selected as the Construction Manager @ Risk by the City of High Point and is seeking to pre-qualify construction trade contractors to submit bids for furnishing labor, materials, equipment and tools for the High Point Center for Active Adults project in High Point, NC.
PROJECT DESCRIPTION:
Construction of a new Senior Center, called Center for Active Adults, with the aim being to re-house programs currently offered at the Roy B. Culler Jr. Senior Center (currently located at the former Oak Hollow Mall) and allow for new offerings and opportunities for active adults, ages 50 and up. This new center will house various lounge areas serving different purposes, large multipurpose space, storage areas, a catering kitchen, art studio, office & conference space and a fitness area & studio with a walking track. Exterior scope to include relocation of community garden, new pickleball court, paving and all associated sitework.
Principal trade contractors are solicited for the following bid packages:
Bid Package
BP0100
Bid Package Description
General Trades
Estimated Budget
$180,000.00
Bid Package
BP0300
Bid Package Description
Concrete
Estimated Budget
$490,000.00
Bid Package
BP0400
Bid Package Description
Masonry
Estimated Budget
$265,000.00
Bid Package
BP0500
Bid Package Description
Structural & Misc. Metals
Estimated Budget
$805,000.00
Bid Package
BP0622
Bid Package Description
Millwork & Casework
Estimated Budget
$102,000.00
Bid Package
BP0710
Bid Package Description
Waterproofing & Caulking
Estimated Budget
$49,500.00
Bid Package
BP0744
Bid Package Description
Siding & Soffits
Estimated Budget
$642,000.00
Bid Package
BP0750
Bid Package Description
Roofing
Estimated Budget
$519,000.00
Bid Package
BP0762
Bid Package Description
Metal Wall Panels
Estimated Budget
$517,000.00
Bid Package
BP0810
Bid Package Description
Doors, Frames & Hardware
Estimated Budget
$10,000.00
Bid Package
BP0840
Bid Package Description
Curtainwall, Storefront & Glazing
Estimated Budget
$183,000.00
Bid Package
BP0925
Bid Package Description
Framing, Drywall & Ceilings
Estimated Budget
$758,000.00
Bid Package
BP0960
Bid Package Description
Flooring
Estimated Budget
$126,000.00
Bid Package
BP0990
Bid Package Description
Painting
Estimated Budget
$56,000.00
Bid Package
BP1000
Bid Package Description
Specialties – Turnkey
Estimated Budget
$18,000.00
Bid Package
BP1022
Bid Package Description
Operable Partitions
Estimated Budget
$43,000.00
Bid Package
BP1140
Bid Package Description
Kitchen Equipment
Estimated Budget
$31,000.00
Bid Package
BP2100
Bid Package Description
Fire Protection
Estimated Budget
$84,000.00
Bid Package
BP2200
Bid Package Description
Plumbing
Estimated Budget
$274,000.00
Bid Package
BP2300
Bid Package Description
HVAC
Estimated Budget
$670,000.00
Bid Package
BP2600
Bid Package Description
Electrical
Estimated Budget
$543,000.00
Bid Package
BP2721
Bid Package Description
Fire Alarm System
Estimated Budget
$56,000.00
Bid Package
BP3100
Bid Package Description
Earthwork
Estimated Budget
$495,000.00
Bid Package
BP3212
Bid Package Description
Paving
Estimated Budget
$342,000.00
Bid Package
BP3218
Bid Package Description
Pickleball Court Finishes
Estimated Budget
$71,000.00
Bid Package
BP3231
Bid Package Description
Fences
Estimated Budget
$50,000.00
Bid Package
BP3290
Bid Package Description
Landscape & Site Furnishings
Estimated Budget
$45,000.00
Bid Package
BP3300
Bid Package Description
Site Utilities
Estimated Budget
$522,000.00
Additional packages may be added and deleted by the Owner and Construction Manager.
Information regarding a Project Information Session & Networking Opportunity are forthcoming and will be shared at a later date.
Blum Construction has a long-standing commitment to maximize minority and other HUB participation on all our projects, and we recognize the importance City of High Point places on minority and HUB participation. There is an established 15% MWBE participation goal on this project. Historically underutilized and minority business participation is strongly encouraged. If MWBE subcontractors require assistance with bonding or payment terms, please let us know. Blum Construction has the ability to create custom solutions to support a successful project outcome. Examples of Trade Partner Support include quick pay arrangements, modified insurance limits, bonding access or alternative bonding solutions, joint check agreements, prequalification assistance, disaggregation of bid packages, alternate options for financial statements prequalification requirements, break out of materials and equipment to support cash flow.
Prequalification forms can be obtained through our online plan room at https://www.flblum.com/subcontractors/ .
Completed prequalification forms should be submitted to Lauren by March 28, 2025. For any questions, please contact Lauren Ashley ([email protected]).
Target bid date is June 2025.